Exit truck road opened by MDOT at Ambassador Bridge Gateway plaza
By Peter Samuel on May 16, 2012
2012-05-15: Michigan state officials celebrated today opening of a two lane truck road that provides a route inside the plaza area that allows trucks from Canada using the Ambassador Bridge to get onto the I-75 interstate without using local streets. Traffic engineers tend to call such routes direct connectors, but this one is anything but direct.
Michigan DOT to solicit D-B bids for approx $16m completion of Ambassador Bridge Gateway
By Peter Samuel on March 14, 2012
Following last week's ruling by county judge Prentis Edwards Michigan DOT is moving to find a design-build contractor to complete work within the bridge company plaza area. The work which the private bridge company estimated to cost it $6m has been costed at $16m using the state's procurement procedures.